This contract serves as an exemption and is outside of normal HBC Contract Procedure Rules. The Damboard Replacement Project began in 2021 and original optioneering was carried out by Beckett Rankine. Beckett Rankine completed a detailed design in 2024 and it was recommended to carry out Ground Investigation work. This was delayed until 2025 as the estimate for the cost of the stoplogs was well in excess of the available budget and a decision by the board was needed to re-establish the project s...